top of page

STOCKYARD HILL WIND FARM

SNC-LAVALIN/WBHO JOINT VENTURE

The $700 million project consisted of 149 approved wind turbines located approximately 35 km west of Ballarat. The Stockyard Hill Wind Farm has the potential to harness one of Victoria’s best wind resources and will provide substantial environmental, community and economic benefits, and will have the potential to power approximately 390,000 homes annually.
The project commenced construction in May 2018.

Tooheys Form-crete were subcontracted to build the turbine bases for the turbines being installed.

Scope of works included:

  • Blinding the base of the excavation

  • Bolt and ring installation

  • Reinforcement installation

  • Conduit and sleeve installation

  • Formwork supply and installation

  • Concrete placement and supply of concrete pumps

  • Stripping of formwork

  • Placement of grout

  • Supply of all cranage for associated tasks

Toohey’s Form-crete completed this scope of works for the Stockyard Hill Wind Farm in 15 months, from August 2018 till October 2019.

STOCKYARDHILL

MT GELLIBRAND WIND FARM

WBHO/CIVILEX JOINT VENTURE

Mt Gellibrand Wind Farm is located 25 kilometres east of Colac and 17km west of Winchelsea in the Colac Otway Shire on Victoria’s Western Plains. The total project value was approximately $258 million, entailing the construction of 44 turbines.


Toohey’s Form-crete were contracted for:

  • Blinding of base of excavation

  • Conduit and sleeve installation

  • Formwork supply and installation

  • Concrete placement and supply of concrete pumps

  • Stripping of formwork

  • Supply of all cranage for associated tasks

Toohey’s Form-crete delivered their completed turbine foundations in 6 months, from June 2017 till November 2017.

MT GELLIBRAND

RAVENHALL PRISON

JOHN HOLLAND GROUP

Ravenhall Prison Project delivered a new medium-security $670 million prison facility to accommodate 1,000 prisoners and was completed in 2017.

GEO Consortium was selected to deliver the project and contracts were signed in September 2014. GEO Consortium comprises GEO Group Australia, John Holland Group, Honeywell and Capella Capital.

Toohey’s Form-crete were contracted by Civilex to complete the forming, pouring and finishing of all landscape pavement including concrete road pavement.

RAVENHALL

MERNDA RAIL EXTENSION

JOHN HOLLAND GROUP

Mernda Station was built as part of the $600 million rail extension of the South Morang line to Mernda, which opened in August 2018.

The station has been built to integrate with the Mernda Town Centre, providing easy access to shopping, entertainment, cafes, restaurants, a library, health and fitness facilities, bus services and the station’s two car parks.

Toohey’s Form-crete were contracted to form, pour and finish the landscape concrete pavement, concrete road pavement and install culvert slabs.

MERNDA

BALLARAT SPORTS AND EVENTS CENTRE (BSEC) 

NICHOLSON CONSTRUCTION

This $24m project was jointly funded by the federal government ($10m) state government ($9m) and the City of Ballarat ($5m)

The project saw six new courts added to the existing two-court Wendouree Sports and Events Centre, making it one of the biggest facilities in the region.

Tooheys Form-crete was contracted to facilitate and complete the concrete foundations of the building and courts, as well as build the tier seating base on the show court.

Scope of Works:

  • Excavation of footings

  • Prepping of bases

  • Form, pour and finish concrete

  • Supply of all materials for associated tasks, including reinforcement and concrete