HANWHA - ACE STAGE 1
BUILT
The $170 million Hanwha Armoured Vehicle Centre of Excellence (H-ACE) is located next to Avalon Airport in Geelong. Once completed the 32,000m2 facility will initially be focused on the production of Hanwha’s AS9 self-propelled howitzer and AS10 Armoured Ammunition Resupply vehicles with capacity for future expansion.
The facility includes:
-
multiple assembly and production lines
-
a 1,500-metre test track
-
a deep-water test facility
-
an R&D center and;
-
an obstacle course to test capability
Toohey’s Form-crete have been contracted to deliver the concrete package for the facility including:
-
Excavation and pouring of all pad footings, strip footings, rafts and beams to ground slabs
-
Supply of all reinforcement and concrete
-
FRP ground slabs approx. 18,000m2
-
FRP suspended post tensioned slab approx. 2775m2
-
Pour and finish in-situ columns and Stairmaster’s
Supply, pour and finish all concrete approx. 10,000m3