MT GELLIBRAND WIND FARM

WBHO/CIVILEX JOINT VENTURE

Mt Gellibrand Wind Farm is located 25 kilometres east of Colac and 17km west of Winchelsea in the Colac Otway Shire on Victoria’s Western Plains. The total project value was approximately $258 million, entailing the construction of 44 turbines.


Toohey’s Form-crete were contracted for:

  • Blinding of base of excavation

  • Conduit and sleeve installation

  • Formwork supply and installation

  • Concrete placement and supply of concrete pumps

  • Stripping of formwork

  • Supply of all cranage for associated tasks

Toohey’s Form-crete delivered their completed turbine foundations in 6 months, from June 2017 till November 2017.