The $10 million early works package for the Bendigo Law Courts entailed the excavation and construction of a perimeter capping beam footing which then enabled the excavation and pouring of basement slab which was delivered on a very limited timeframe.
Toohey’s Form-Crete were contracted to deliver:
Supply and installation of reinforcement to perimeter capping beam and basement slab
Supply and installation of all formwork
Supply, pouring and finishing of all concrete