The Geelong Premixed Concrete Plant owned and operated by Barro Group is a concrete batching plant that services the wider Geelong region.

The redevelopment includes an extension to the existing batch plant including new buildings, pavement and material storage facilities.

 

Toohey’s Form-Crete were contracted to deliver:

 

  • All excavation including site cut, subgrade prep, bored piles and footings.

  • Supply, place and compact CTCR base prep to all new paving  

  • Installation of precast panels to the new storage bins

  • FRP new conveyor pit and associated works

  • Pour and finish concrete paving approx. 7,000m2