Mt Gellibrand Wind Farm
WBHO / Civilex JV
Mt Gellibrand Wind Farm is located 25 kilometres east of Colac and 17km west of Winchelsea in the Colac Otway Shire on Victoria’s Western Plains. The total project value was approximately $258 million, entailing the construction of 44 turbines.
Toohey’s Form-crete were contracted for:
Blinding of base of excavation
Conduit and sleeve installation
Formwork supply and installation
Concrete placement and supply of concrete pumps
Stripping of formwork
Supply of all cranage for associated tasks
Toohey’s Form-crete delivered their completed turbine foundations in 6 months, from June 2017 till November 2017.